السلام عليكم
لدى سؤال فى ال time cliam

Activity 1-IFC, Planned Received IFC(Excavation): 1-July-2007, duration of the Activity A (Excavation) :50days ,planned start date: 15-
July-2007

Activity B, IFC of Foundation
Planned received date: 20-July-07

Activity C, Concrete Foundation
Duration of concrete:70days, Planned Started F.S with the Excavation

but the IFC Rev were
Rev.1 Excavation dated 1-July-08+
Rev.2 Excavation dated 13-July-08
Rev.3 Excavation dated 20-August -08
Rev.4 Excavation dated 28-August-08

Rev. 1 Concrete foundation dated : 25-July-08
Rev. 2 Excavation Dated :28-August -08

with this information
at 20 August:
Progress% Excavation dated : 30%
Concrete: 15% for example

at 28-August
Excavation :90%

Thank you very much
I would like to know the method and procedure for extension time claim and i will consider the update or not

Concrete:90%​
 

MouneerPMP

عضو جديد
إنضم
19 ديسمبر 2005
المشاركات
57
مجموع الإعجابات
6
النقاط
0
what do u mean by:
but the IFC Rev were
Rev.1 Excavation dated 1-July-08+
Rev.2 Excavation dated 13-July-08
Rev.3 Excavation dated 20-August -08
Rev.4 Excavation dated 28-August-08
 

مخطط مشروعات

عضو جديد
إنضم
4 يوليو 2008
المشاركات
3
مجموع الإعجابات
0
النقاط
0
what do u mean by:
but the IFC Rev were
Rev.1 Excavation dated 1-July-08+
Rev.2 Excavation dated 13-July-08
Rev.3 Excavation dated 20-August -08
Rev.4 Excavation dated 28-August-08

IFC means
Issue for contruction
and it were a lot of rev.
قام المالك باصدار IFC مرات كثيرة
الحفر و الخرسانات
و التواريخ كما هو مبين سابقا
و شكرا
 

mohamedsaid78

عضو جديد
إنضم
10 يونيو 2007
المشاركات
71
مجموع الإعجابات
0
النقاط
0
u must refer to your contract conditions about how to calculate the extension of time is it will according to the updated status of the project or according to the Baseline Schedule.
Secondly you must know that in 95 % of the E.O.T u gonna claim only for the negative float u had due to this impact u can't claim for all the delayed period cuz the consaltant in the most of the situtations will not approved an E.O.T for an activity still having +total float after retriving the impact event
 

mos

عضو جديد
إنضم
16 نوفمبر 2005
المشاركات
581
مجموع الإعجابات
25
النقاط
0
أخى الكريم
تمديد وقت المشروع مرتبط بنوعية ومنطوق بنود العقد
وعموما المقاول يستحق التعويض زمنيا و أو ماديا عن التأخير بسبب المالك ere
وللتأخير المعطل فقط للمسار الحرج وليس للمقاول الحق التعويض عن فترات العوم التى هى من حق المشروع.

مع خالص الشكر
 
إنضم
17 يونيو 2008
المشاركات
3
مجموع الإعجابات
0
النقاط
0
u should coordinate with your project contract admin.
usually we use the nearest update to the event
and insert the events that delayed the schedule and compare this scenario with the baseline schedule to get the delay that you will claim from the client.
 